Project Management Dashboard: Five Tiles and Nothing Else
A project management dashboard with five tiles: schedule, money, changes, risks and decisions needed. How to build it in an hour and why green should mean something.

I once sat through a project review where the dashboard had thirty-one tiles, seven colors and a speedometer. The speedometer was for "team velocity." The needle was pointing at "excellent." The project, which I will not name, was three months late. When I asked what the speedometer was measuring, everyone looked at everyone else, and a kind person eventually said, "I think it just looks good." It did. It looked like a car that was not going anywhere.
A dashboard has one job: to help the people who run the project decide something this week. Everything else is decoration, and decoration has a cost, because every tile somebody has to update is time not spent on the project. This article gives you five tiles, a way to build them in an hour, a meaning for each color and a Monday test to check whether your dashboard is honest. It is general information. The project and the numbers in the examples are invented, and I have not reviewed any particular software.
If you want the reasoning behind choosing numbers at all, my guides to dashboards without vanity metrics and data-driven project management go deeper. This article is the build guide: what goes on the page and how to keep it alive.
What a dashboard is for
A dashboard is not a report. A report explains what happened, in paragraphs, for someone who was not there. A dashboard shows where the project stands right now, in a few numbers, for the people who are there and have to decide. If you already write a project status report, the dashboard is its front page: the five answers you would put in the first lines.
Two rules keep it honest.
One page, two minutes. If a person cannot read the whole thing in two minutes and say what is wrong, it is too big. The limit is not about attention spans. It is about what a Friday afternoon can bear.
Every tile answers a question that someone will act on. Before you add a tile, finish the sentence: "If this goes red, then ___ will do ___." If you cannot finish it, the tile is a decoration.
The five tiles
Tile 1: Schedule. Show the next milestone, its date and the days of slack, meaning how many days it can slip before it moves the end date. "Next milestone: permit submitted, Dec 12, 4 days of slack." That one line tells you more than a percent-complete bar, because it points at the thing that is next and says how much room you have. If you want to understand slack and what determines it, the critical path method explains it with a pencil, and the schedule management guide shows how to get from a task list to a baseline.
Tile 2: Money. Three numbers: spent so far, planned to this date and forecast to finish, with the date of the forecast. The forecast matters most, because it is the only one of the three that looks forward. A simple forecast is "what we have spent plus what we think remains," updated every week. If you want a more precise method, earned value in plain English explains it, and project cost management covers the budget and the contingency.
Tile 3: Changes. The number of open change requests and the total price, in time and money, of the ones already approved. This tile is the early warning for scope creep: a project whose approved changes grow every week is turning into a different project. The habits in stopping scope creep fit on this tile.
Tile 4: Risks and issues. The top three, not thirty, each with an owner and what will happen next. A risk is something that might happen; an issue is something that already did. Keep the two apart. The risk register for small business shows how to keep the list behind the tile.
Tile 5: Decisions needed. This is the one I would not remove. A list of the decisions that need making this week, each with a name and a date: "Choose the flooring supplier, Marta, by Wednesday." It turns the dashboard from a mirror into a steering wheel. It is also the quickest way to see whether a project is stuck, because stuck projects accumulate undecided decisions.
That is it. Five tiles, one page. If you feel the urge to add a sixth, write it on a sticky note, put it on your desk and ask yourself on Friday whether it would have changed a decision. In my experience, it almost never does.
What to leave out
The list of things I have seen on dashboards and removed is long, and mostly consists of numbers that are easy to collect and hard to act on. Here are the usual suspects, and what to put in their place.
| A tile that earns its place | A tile that is decoration |
|---|---|
| Days of slack on the next milestone | Percent complete of the whole project |
| Forecast to finish, with the date it was made | A green bar with no number |
| Open change requests, and the cost of those approved | Total hours logged |
| Top three risks, each with an owner and a trigger | A heat map of thirty risks |
| Decisions needed this week, with names | A word cloud of last week's meeting |
- Percent complete. A number that is wrong in a predictable way: the first 90 percent takes 90 percent of the time and the last 10 percent takes the other 90 percent. Use the next milestone and its slack.
- Hours logged. Hours are an input, not a result. A team can log many hours on the wrong thing.
- Heat maps with thirty risks. Nobody reads them. Three risks with owners are better than thirty without.
- Charts of last week. The past is useful only if it informs a decision. Show the trend only if somebody acts on it.
- Anything that nobody updates. A tile that was last refreshed in October is a tombstone.
If you want a longer list of what to avoid, the vanity-metrics article is a good companion.

Make the colors mean something
Most dashboards use green, amber and red, and most of the time the colors mean "how the person who filled it in feels." The result is the famous "watermelon" project: green on the outside, red on the inside. I would rather have three colors with strict meanings.
| Color | What it should mean | What it must come with |
|---|---|---|
| Green | On plan, and I can say how I know | The number and the date it was measured |
| Amber | Heading toward trouble if nothing changes | What changes, and who does it, by when |
| Red | Off plan now; a decision or help is needed | A named owner and the decision wanted |
Green means on plan, and I can say how I know. It must come with a number and a date: "Slack: 4 days, measured Friday."
Amber means heading for trouble unless something changes. It must come with what changes, who does it and by when: "Permit reviewer has not replied. Dana will call Monday. If no answer by Wednesday, red."
Red means off plan now, and a decision or help is needed. It must come with a named owner and the decision wanted: "Flooring is two weeks late. Needs a decision from the owner: wait or switch supplier, by Thursday."
With those rules, red is not a confession. It is a request. That makes it easier to raise, and that, in turn, makes the dashboard more honest. People hide red when red means "you failed." They show red when red means "I need this."
Build it in an hour
You do not need special software. A spreadsheet, a shared document or a single page in a notebook is enough.
- Draw five boxes on one page, with the tile names above.
- Name an owner for each tile. One person, not "the team." The owner updates the tile on a fixed day, such as Thursday at noon.
- Write today's values, with the date and source next to each number. Take ten minutes per tile, no more. If a number is not available, write "not known" and the date you will know.
- Pick the colors with the rules above.
- Add the decisions-needed list last, from what the other four tiles tell you.
- Put it on the agenda. The dashboard is the first item of the weekly meeting, and the weekly meeting has a fixed day. The 30-minute weekly rhythm gives an agenda.
The update takes about ten minutes once a week. If it takes longer, check whether you have more than five tiles or whether the numbers live in too many places.
An invented example. Lakeview Bakery (an invented name) is opening a second counter inside a hotel lobby. The owner, Ana, builds the page: the next milestone is the health inspection on January 9, with six days of slack. The money tile shows spent 14,200, planned 15,000 and forecast 31,500 against a budget of 30,000, with the date. Changes: two open, one approved for 900 and four days. Risks: the display case delivery, one person who knows the oven, and the inspector's availability, each with an owner. Decisions needed: choose the signage vendor by Wednesday (Ana), approve or decline the second change by Friday (Ana and the hotel manager). That is the whole page, and in two minutes the team knows where it stands and what to decide.

The dashboard and the people
A word on who sees it. A dashboard that only the project manager reads becomes a private diary. Share it with the people who can decide and the people who do the work: the owner, the sponsor, the team leads. If your project has a sponsor, the guide to keeping the executive sponsor engaged explains how to use a short page to hold their attention, and the stakeholder map helps you decide who else needs to see it.
Also decide who is allowed to say "red." If only the project manager may do it, the page will be green until the day it is a disaster. A team where anyone can turn a tile red, with the information that goes with it, hears about problems early. That is the single most important cultural effect of a good dashboard, and it costs nothing.
Finally, talk about the page, not only fill it in. The point of the Friday ten minutes is not the update. It is the conversation it starts. A dashboard on a screen that nobody discusses is wallpaper.
The Friday ten minutes, minute by minute
A habit is easier to keep when you can see its shape. Here is the ten-minute update I use, and you can steal it.
- Minute 1. Open the page and read the date at the top. If it is more than a week old, say so out loud. That alone prevents tombstones.
- Minutes 2 and 3. Update the schedule tile: the next milestone, its date, the days of slack. Look at the plan, not at your memory.
- Minutes 4 and 5. Update the money tile: spent, planned, forecast to finish. If the forecast moved, write why in one line.
- Minute 6. Count the open change requests and the approved ones. If the approved list grew, ask whether the project is still the project.
- Minutes 7 and 8. Re-rank the top three risks and issues. Remove one that no longer matters, add one that does, check that each has an owner.
- Minutes 9 and 10. Write the decisions needed, with a name and a day. Then send the page to the people who decide, with one sentence: "The one thing I need from you is ___."
The last sentence is the secret. A dashboard that arrives with a request gets read. A dashboard that arrives as an attachment gets filed. And if the page is quiet for three weeks in a row, that is not a sign that all is well. It is a sign to ask whether the tiles still measure the things that matter.
When you need more than five
Large projects, programs and portfolios will want more: resource use, quality metrics, benefits tracking, dependencies between projects. That is fine, and it is a different article. The way to grow without losing the point is to keep the front page at five tiles and put the extra detail behind it, one level down, for the people who need it. If your organization runs several projects, the difference between project and program management matters here, and so does lightweight governance, which keeps the decision rights simple. For a long-term view of whether the work paid off, the article on benefits realization takes over after the project ends.
The hall of fame of dashboard mistakes
- The speedometer. A visual that looks like measurement and measures nothing.
- The watermelon. Green outside, red inside, because red is considered rude.
- The tombstone. A tile last updated three months ago, still green.
- The thirty-tile wall. Nobody can find the one that matters.
- The dashboard without owners. Everybody's job, so nobody's job.
- The dashboard without decisions. A mirror, however handsome.
- The tool before the page. An expensive platform bought before anyone wrote what the five tiles are.
Try it: would your dashboard pass the Monday test?
Tick every statement that is true of the dashboard or status page you use today. The unticked ones are where it is decoration.
What to do this week
Take the dashboard you have, or the status page you wish you had, and cut it to five tiles. Give each tile an owner and a day. Write the decisions-needed list, even if it is short. Add the date and source to every number, and write what each color has to mean. Then run the Monday test above. If you score low, do not add anything. Take away until what is left is honest.
If you would like a second pair of eyes on yours, tell me about the project and I will say honestly whether I can help. My services page says what I do and do not do, the two-minute diagnostic shows which engine of your business needs attention first, and the free templates include one-page sheets for a status page and a decision log.
Which tile on your current dashboard has never once changed a decision? Tell me in the comments. I read every one, and I will not ask about the speedometer.
General information. The project, the people and the numbers in the examples are invented, and I have not reviewed any particular software or vendor. Tools, prices and features change, so check each provider directly before you decide.
Frequently asked questions
What should a project management dashboard include?
Five tiles are enough for most small and mid-sized projects: schedule (the next milestone and its days of slack), money (spent, planned and forecast to finish, with the date), changes (open requests and the price of approved ones), risks and issues (the top three with owners) and decisions needed this week with names. Anything else should earn its place by changing a decision.
How do you build a project dashboard quickly?
Draw five boxes on one page, name one owner per tile, write today's numbers with the date and source, set the colors using strict meanings, add the decisions-needed list and put the page at the start of the weekly meeting. A spreadsheet or a shared document is enough, and the weekly update should take about ten minutes.
What do red, amber and green mean on a project dashboard?
Green should mean on plan, with a number and date that show how you know. Amber means heading for trouble unless something changes, with what changes, who does it and by when. Red means off plan now, with a named owner and the decision or help needed. Colors without those details are opinions.
What is the watermelon effect in project reporting?
A project that reports green on the outside while the real situation is red on the inside. It happens when red is treated as blame. Making red a request for a decision or help, with a name attached, and letting anyone turn a tile red with the supporting information, tends to surface problems earlier.
Everything new, once a month.
One email on the 1st of every month with everything new: articles, series parts, news, website updates, project results, where I am working and the business opportunities I am looking at. No spam.
- Fresh on the site right now
- ArticlePMBOK Step by Step, Part 6: Running the Work, Executing and Managing the Team
- NewsA second $2 million loan for a Main Street rebuild: what a project manager sees in a stack of money
- SeriesRunning the work: executing and managing the team
Join the conversation
Did this help? A quick reaction tells me what to write next.
Be the first to react.

Loading comments…