PMBOK Step by Step, Part 6: Running the Work, Executing and Managing the Team

Part 6 follows the invented Riverside clinic into execution: five habits for running the work, a change request priced in days and dollars, and how to manage a team.

Six wooden rowing oars leaning in a neat line against a weathered wooden boathouse wall at dawn, with calm water in the distance
A team moves when the oars are in the water at the same time. Running the work is mostly about the rhythm.

The plan survived until 7:40 on the first morning of construction. At 7:40, the contractor's crew lead (invented, like the rest of this story) asked a perfectly reasonable question: "Which door do you want the delivery through?" Nobody on the Riverside team had decided, because everyone had assumed somebody else had. The plan said "deliver materials." It did not say where, and the delivery truck was already idling at the curb, politely, with the engine running. That is execution. It is not a Gantt chart. It is a truck, a door and a question that nobody wrote down.

This is Part 6 of PMBOK step by step, which follows one invented clinic project from idea to closeout. In Part 1 the owners of the Riverside Family Clinic signed a charter with a budget of $280,000. In Part 2 they listed who is involved, in Part 3 they described the work and in Part 4 they set a schedule and a cost baseline. In Part 5 they wrote a risk register. Now the planning stops and the doing starts.

A reminder: the clinic is invented. Riverside is a composite, not a real client, and all names and numbers are illustrative. Nothing here is legal, financial or medical advice.

Where this sits on the PMBOK map

In the older process-group view of the PMBOK Guide (the 6th edition), executing was the group that held the processes for directing and managing the project work, managing quality, acquiring and developing the team, managing communications, implementing risk responses, running procurements and managing stakeholder engagement. It was the longest and busiest group, because it is where most of the money and most of the people live.

The 8th edition of the Guide changed how it presents this. As PMI's public page describes it, the process guidance is non-prescriptive, meaning a menu to tailor and not a checklist to obey. In the free field guide I am writing, I read execution through a map: the Governance row has a process called Manage Project Execution (1.4 on the map, which I mark as my reading to confirm in the Guide), and the other domains each contribute their own part. If you want that view, the field guide hub and its chapter on the five focus areas and how to read the map are the place to start.

Whatever edition you follow, the work itself is the same: people do things, things change, and someone keeps the plan honest. That is what the rest of this part is about.

The five habits of a project that is running

I keep a short list. It is my own, not a standard, and it fits on a napkin.

1Kick off and agreeGoal, dates, who decides
2Keep the rhythm30 minutes a week
3One listIssues, decisions, changes
4Price every changeIn days and dollars
5Check quality in the workBefore it is built over
The five habits of running the work. Each one answers a way projects usually drift.

Habit 1: Kick off with the whole team, and write the team agreement

The kickoff is the day the plan becomes a shared picture. Everyone is in the room (or on the call), someone reads the charter aloud, and each person says one thing that could stop them. I have a standard question I ask at every kickoff, and it is always worth the ten minutes: "What is the thing you are worried about, but nobody has asked you?" On the Riverside project, the answer from the electrician was "the panel in the old building has no label, and nobody knows what is on it." That was not on any list, and it took one afternoon to fix because it was said on day one.

Then write a team agreement on one page. It is not a contract. It is five lines: how we talk (one channel, not three), how fast we answer (same day for questions that block someone), how we say "I am stuck" (early, without apology), who decides what and how we handle disagreement. It feels corporate for about a day and then becomes the thing people point to when something goes wrong. For the whole-team picture of who is responsible for what, a RACI chart is a good partner, and the kickoff meeting agenda gives a 60-minute plan.

Habit 2: Keep the rhythm

A weekly meeting, 30 minutes, same day, same agenda. It starts with the dashboard (five tiles: schedule, money, changes, risks and decisions needed; the guide to a project dashboard with five tiles shows how), then the decisions that must be made this week and who makes them. Nothing else. If someone wants to talk about a long topic, they book a separate meeting with the people who matter for it.

The rhythm matters more than the content, because it is the thing that makes problems visible while they are small. For the template, the weekly rhythm article gives a full agenda. On Riverside, the Monday meeting at 8:15 caught the truck-and-door problem on the second Monday, not the second month.

Habit 3: One list

Issues, decisions and changes live in one list, in one place, with an owner and a date on every item. Not three lists in three tools. I have seen projects with a decision log in a spreadsheet, an issue list in an email thread and a change log in a binder, and the result is that none of them is complete, and the project manager spends Friday afternoons reconciling them like a bank teller after a strange day.

An item has five fields: what it is, who owns it, the date by which it must be resolved, its status and the next step. A decision that needs to be made is a line with a name. An issue that is open is a line with a name. A change that is requested is a line with a name and a price. If a line has no name, it is not on the list yet.

Habit 4: Price every change

Changes are normal. The problem is not that a project changes. It is that a change arrives as a friendly suggestion and is approved with a nod, and its cost arrives later as a surprise. The cure is a rule, applied without exception: no change is approved before it has a price in time, money and risk, and the decision is written down.

Here is an invented example from Riverside, in the form I would use.

The change requestUpgrade the exam-room flooring (invented)
Who asked, and whyThe contractor, for easier cleaning
Cost$4,200, from contingency
TimeAdds 5 working days, not on the critical path
RiskThe material is on back order
DecisionApprove for two rooms only. Owner, Friday, in writing
A change request priced in days and dollars. The decision names a person and a day.

Notice what happened. A friendly suggestion from the contractor became a priced option with a clear decision: approve for two rooms only, owner decides on Friday, in writing. The owner could have said yes to all four rooms in the hallway, and the answer would have been a $4,200 mistake multiplied by two. The rule costs five minutes and has saved me many times. If you want the habits for the harder conversations around scope, the guide to stopping scope creep gives the sentences, and change orders in construction shows the formal side.

Habit 5: Check quality inside the work

Quality is checked while the work is happening, not at the end when it is covered by drywall. On Riverside, the inspection of the first exam room's plumbing before the walls closed took twenty minutes and found a reversed fitting. Fixing it then cost nothing. Finding it after the walls closed would have cost a wall.

The rule: define what "done" means for each piece of work before it starts (one line), and check one real piece early. An early check is a cheap experiment, and it also teaches the team what "good" looks like, which is the most effective quality program I know.

When a risk wakes up

In Part 5, the Riverside team listed the risks, including a permit delay, and wrote a trigger for each. In week six of construction, the trigger fired: the city's permit office had not replied in ten business days, which was the number the team had written down. Because the trigger was written, nobody had to argue about whether it was time to worry. It was. The risk had become an issue, and the issue went onto the one list with an owner and a date.

The response had been planned: meet the city office. The owner called, found that a form was missing a signature and fixed it in an afternoon. The cost of the issue was three days. Without the trigger, it would probably have been discovered at week ten, when the cost would have been three weeks. A written trigger is a way of agreeing, in advance and calmly, on the day you will stop hoping. For the register and the triggers, the Part 5 article and the risk register for small business are the references.

A long empty meeting table with six chairs and a blank white whiteboard on the wall in a bright room
The weekly meeting needs a table and a fixed time. The agenda is on the wall, and it is short.

Managing the team

Everything above is about the work. A project is also people, and people do not run on dashboards. Four things matter most, and none of them needs a certification.

Clarity. Most of the tension I see in teams comes from not knowing who decides. A line in the team agreement, a RACI chart and a decision list resolve most of it. When two people think they own the same decision, no amount of friendliness helps.

Delegation as a ladder. Delegation is not a switch between "I do it" and "you do it." I use four rungs.

Level of delegationWhat it sounds likeUse it when
1. Do it my way"Here are the steps."New person, high risk
2. Recommend, I decide"Bring me two options and your pick."Learning the work
3. Decide, then tell me"Choose, then tell me by Friday."Trusted, moderate stakes
4. Decide on your own"This one is yours."Proven, low stakes
The delegation ladder. Move people up as they prove it, and say out loud which rung you are on.

New people, or high-risk work, start at rung 1 or 2. Proven people, with low stakes, can be at rung 4. The useful part is saying the rung out loud: "On this one, bring me two options and your pick." It removes the guessing that makes people either freeze or overreach.

A short one-to-one. Fifteen minutes, every two or three weeks, with one question: what is in your way? Then listen. Do not solve it in the room unless it is small. Write it down and come back with an answer. A one-to-one is the cheapest early-warning system I know, because people say things in private that they will not say in a meeting. If you want to dig into the people side of a project, the article on change management, the people side has more, and the new guide to a change management process for small teams is useful when the work asks people to behave differently.

Attention to the edges. The people at the edge of the project, such as the part-timer, the contractor and the person in another office, are the ones who find out last. Make a habit of asking them first. Also remember the people outside the team: the stakeholder register from Part 2 should be read every few weeks, and the person who stopped answering your emails is usually the one to call.

Conflict, when it comes, is best met early and privately, with the facts and with the project's goal, not with the person's character. "The drawings and the schedule disagree about the delivery date. Which one is right?" is a better opening than "You always do this."

Keeping the plan alive

The plan from Parts 3 to 5 is a baseline: a snapshot of what you intended. Reality will drift from it. Do not pretend it does not, and do not rewrite the baseline every time something changes. Here is the rule I use: update the forecast every week, and re-baseline only when a change is approved. The forecast says what you now expect. The baseline says what you agreed. The difference between them is the news. If you rewrite the baseline silently, you lose the news.

When a major change is approved, such as the owner choosing to phase the opening, you do re-baseline, and you write why. The project management plan guide explains how the pieces fit, and lightweight governance shows how to keep the decision rights simple.

A pair of leather work gloves resting on a wooden sawhorse beside a yellow spirit level in a clean workshop
Check the work while you can still reach it. A level on the first wall is cheaper than a level on the last one.

The hall of fame of execution mistakes

  • The plan that says "deliver materials" and not where. The truck is idling.
  • Three lists in three tools. The project manager's Friday is spent reconciling.
  • The nodded change. A friendly suggestion approved without a price.
  • The meeting that became a story hour. Thirty minutes grew to ninety, and nobody decided anything.
  • The heroic fix. One person works every night, and the project looks fine until they get sick.
  • Quality at the end. The wall is already closed.
  • The silent baseline rewrite. The plan always says "on track" because the plan changed.
  • The one-to-one that never happens. The first time you ask what is in someone's way is at their resignation.

Try it: your first four weeks of running the work

Pick the day execution starts, and the tool gives you the steps of a sensible first month, with a date for each. Move any date to fit your project.

Interactive tool

Your first four weeks of running the work

Loading the tool…

What to do this week

If a project is already running, run it against the five habits. Is there a team agreement on one page? A weekly meeting with a fixed time? One list? A rule that no change is approved without a price? A quality check inside the work? Pick the one that is missing and add it on Monday. If you are about to start a project, put the five habits on the kickoff agenda and write the team agreement before anything else.

If you would like help setting up the habits for a real project, tell me about it and I will say honestly whether I can help. My services page says what I do and do not do, the two-minute diagnostic shows which engine of your business needs attention first, and the free templates include one-page sheets for the weekly meeting and the change log. Next Wednesday, in Part 7, the Riverside team starts keeping score: monitoring the work and controlling it when it drifts.

Which of the five habits would have saved your last project a week, and which one do you skip when you are busy? Tell me in the comments. I read every one, and I will not tell the truck driver.

The Riverside Family Clinic is an invented example, and all figures and names are illustrative. General information, not legal, financial or medical advice. PMBOK and PMP are registered marks of the Project Management Institute, Inc. This series is independent and is not affiliated with, or endorsed by, PMI.

Frequently asked questions

What does executing mean in project management?

Executing is doing the planned work and keeping the plan honest while it changes. In the older PMBOK process-group view it covered directing and managing the project work, managing quality, building and managing the team, managing communications, implementing risk responses, running procurements and managing stakeholder engagement. In practice it comes down to a rhythm, one list, priced changes and checks inside the work.

How do you manage project changes during execution?

Price every change request in time, money and risk before anyone approves it, write the decision with a name and a date, and keep one change log. A friendly suggestion approved without a price becomes a surprise cost later. Update the forecast every week, and re-baseline only when a change is approved.

How do you manage a project team?

Start with clarity about who decides what, use delegation as a ladder from "do it my way" to "decide on your own" and say out loud which rung you are on, hold a short one-to-one every two or three weeks that asks what is in the way and check in with people at the edges of the project first. Meet conflict early and privately, with facts and the project goal.

What is the difference between a risk and an issue?

A risk is something that might happen. An issue is something that already did. A written trigger, such as ten business days without a reply from the permit office, tells you the day a risk has become an issue, so you act on a planned day instead of the day you finally admit the problem.

Monthly newsletterNext issue · Dec 1

Everything new, once a month.

One email on the 1st of every month with everything new: articles, series parts, news, website updates, project results, where I am working and the business opportunities I am looking at. No spam.

  • Fresh on the site right now
  • ArticlePMBOK Step by Step, Part 6: Running the Work, Executing and Managing the Team
  • NewsA second $2 million loan for a Main Street rebuild: what a project manager sees in a stack of money
  • SeriesRunning the work: executing and managing the team

One email a month, on the 1st. Leave any time.

Join the conversation

Did this help? A quick reaction tells me what to write next.

Be the first to react.

Comments

Loading comments…

Leave a comment

No email and no sign-up. Every comment is reviewed before it appears. Please keep it respectful and leave links out.

Keep reading

More ideas you may like.

Keep exploring

Related projects and services.

Next step

Let's find the project that moves your business.

Tell me where things are stuck. I will tell you which project I would start with.