Measure what matters: 6 figures.
Pick the few numbers that change decisions, track real progress and build dashboards that tell the truth.
In this topic: Project Cost Management: Budget, Baseline and Contingency · Data-Driven Project Management: Measure What Moves the Result · Earned Value in Plain English: Know If a Project Is Really on Track · Dashboards Without Vanity Metrics: What Leaders Should Actually Watch
Nov 12, 2026 · 3 figures
Project Cost Management: Budget, Baseline and Contingency
At week 5 (dashed line): planned work about $26k (black dot on the curve), work done $22k (accent dot), paid $21k and committed $41k.
Oct 19, 2026 · 1 figure
Data-Driven Project Management: Measure What Moves the Result
| Project | Outcome | Progress | Health |
|---|---|---|---|
| A restaurant opening | Covers served in the first month | Percentage of opening checklist items done | Open critical issues, such as permits or equipment |
| A road maintenance program | Kilometers completed to specification | Milestones met on their planned date | Cost variance against budget |
| An exploration drilling program | Meters drilled and logged with approved results | Holes completed against plan | Core recovery and lab turnaround time |
| A startup sprint | Paying customers | Qualified conversations started per week | Share of the week spent on the three chosen projects |
| A process improvement | Hours saved per week | Steps automated | Exceptions people had to handle by hand |
Oct 19, 2026 · 1 figure
Earned Value in Plain English: Know If a Project Is Really on Track
Budget at completion (BAC)The total approved budget for the work.
Planned value (PV)The value of the work you planned to have finished by today.
Earned value (EV)The value of the work you have actually finished by today, measured in budget terms.
Actual cost (AC)What you have actually spent so far.
Oct 19, 2026 · 1 figure
Dashboards Without Vanity Metrics: What Leaders Should Actually Watch
Which decision will this number support?If the answer is vague, such as "to keep an eye on things," decline politely.
Who will own it?A number without a named person drifts out of date within weeks.
Where will the data come from?If it needs manual re-entry every week, it will not survive the first busy month.
What will we do when it goes red?If there is no planned response, the number is only a way to feel worse.
What will we stop watching to make room for it?A dashboard is a budget of attention.