Practice · 15 cards so far

Practice cards that explain themselves.

Original questions in the style of a scenario test. They are not copies of any real exam, and none comes from leaked or "dump" material. Swipe through the deck, pick an answer, then walk through the explanation one step at a time.

0 answered0 right
Swipe, or use the arrows

Practice cardRecall from PMI's page

PMI published a list of what is new in the PMP exam it updated in July 2026. Which statement matches that list?

How sure are you?

Read it like a test-taker

The phrase that decides the question is what is new. Study habit: words like "only" and "drops" often signal an option that is too strong. Check them against what you know.

Why B is the best answer

PMI's page lists new domain weights: People from 42% down to 33%, Process from 50% down to 41% and Business Environment from 8% up to 26%. It also lists AI, sustainability and stakeholder engagement in project-based scenarios.

Why the others fall short

  • AThe update adds topics to project-based scenarios. It does not remove them.
  • CPMI says the exam content outline defines what is tested, and that the core principles and approaches have not changed. The word "only" is the clue that the option is too strong.
  • DThe direction is reversed. People went from 42% down to 33%.

Where this question lives on the map

This question is about the whole map, not one process.

The same idea in a small business

In your own business, ask whether more of your time now goes to customers, money and results than to tasks. That is the same shift.

Practice cardScenario

A five-person team is told to apply all 40 processes in full to a two-week project. What is the best response?

How sure are you?

Read it like a test-taker

The phrase that decides the question is all 40 processes in full. Study habit: "best" usually means the answer that fits the situation, not the most thorough one.

Why B is the best answer

PMI describes the process guidance as non-prescriptive, which means it is meant to be adapted. Tailoring keeps the parts that earn their keep and records the choice, so the team can defend it later.

Why the others fall short

  • AThe paperwork would cost more than the work. A guide that is non-prescriptive is not asking for every process in full.
  • CTailoring is not the same as no process. The basics stay: an owner, the key numbers, a rhythm and a rule for change.
  • DNothing in the situation calls for a PMO, and stopping a two-week project to build one would only add delay.

Where this question lives on the map

This question is about the whole map, not one process.

The same idea in a small business

A two-week job gets one page and a Friday check, not a binder.

Practice cardProcess 1.8 · Assess and Implement ChangesScenario

Halfway through a project, the sponsor asks for an extra report format. The team lead says yes on the spot. What was missing?

How sure are you?

Read it like a test-taker

The phrase that decides the question is says yes on the spot. Study habit: when a question describes a quick yes or a quick no, the missing step is often the assessment that should have come first.

Why A is the best answer

Assessing and implementing changes means looking at each request, understanding what it does to the plan and deciding through the agreed route. Saying yes on the spot skips the price tag, so someone pays later, usually with a weekend.

Why the others fall short

  • BA longer meeting does not assess anything. It only makes the same shortcut take longer.
  • CA risk register is useful, but the gap here is the missing look at the change.
  • DThe sponsor did nothing wrong by asking. The gap is in how the request was handled.

Where this question lives on the map

1.8 Assess and Implement Changes
Look at every change request, say yes, no or later, and update the plans when the answer is yes.

The same idea in a small business

A customer asks for one more thing and you say yes. The price in time and money is paid by someone, so name that someone before you answer.

Practice cardScenario

A team delivers every item on the specification, but the customer says they cannot use the result to solve their problem. Which principle was neglected most?

How sure are you?

Read it like a test-taker

The phrase that decides the question is cannot use the result. Study habit: find the one phrase that names the symptom, and ask which principle is about that symptom.

Why A is the best answer

Delivering every item is output. Value is whether someone is better off, and the customer cannot use the result to solve their problem. The principle about what the work is for is the one that failed.

Why the others fall short

  • BNothing in the situation points to long-term cost or impact. The problem is usefulness today.
  • CThe question does not say that nobody answered for the work. It says the result is not useful.
  • DThe team delivered everything on the list, so there is no sign that it lacked authority.

Where this question lives on the map

This question is about the whole map, not one process.

The same idea in a small business

A customer who gets exactly what they asked for and still cannot use it is a sign that you asked for the wrong thing.

Practice cardScenario

During testing, a team finds that the product fails a requirement. The manager says, "We will fix it after launch so we hit the date." Which principle does this conflict with most directly?

How sure are you?

Read it like a test-taker

The phrase that decides the question is fix it after launch. Study habit: when two options both seem possible, choose the one that matches the symptom most directly.

Why A is the best answer

Embedding quality means building it in as the work goes, not checking and repairing it after the money is spent. Postponing a known failure to a later date is the opposite.

Why the others fall short

  • BSustainability is about what the project leaves behind. A known defect does affect that, but the more direct conflict is with building quality in.
  • CThe team did its job: it found the failure. The decision to postpone was the manager's.
  • DA holistic view matters, but the symptom described, a known failure pushed past the launch, is a quality question first.

Where this question lives on the map

This question is about the whole map, not one process.

The same idea in a small business

A known defect with a date attached is a debt. Write down who pays it and when.

Practice cardProcess 6.4 · Lead the TeamScenario

A project manager personally approves every small decision, and the team waits days for answers. Which principle is being undermined?

How sure are you?

Read it like a test-taker

The phrase that decides the question is personally approves every small decision. Study habit: "every" is often the word that tells you where the problem is.

Why B is the best answer

Empowered teams can decide what they are best placed to decide. A single approver for every small decision makes the whole project move at the speed of one person's inbox.

Why the others fall short

  • AThe scenario does not say anything about whether the result will be useful.
  • CWaiting does not mean the quality is bad. It means the decisions are slow.
  • DNothing in the scenario concerns what the project leaves behind.

Where this question lives on the map

6.4 Lead the Team
Develop the team, build trust and resolve conflict so people do good work together.

The same idea in a small business

Write down which five decisions the team can make without asking you, and which three still need you.

Practice cardScenario

A team lead says, "We are in Executing, so planning is over." A key supplier then moves its delivery date by three weeks. What is the best reading of the focus areas?

How sure are you?

Read it like a test-taker

The phrase that decides the question is planning is over. Study habit: when an option says "for good" or "all", ask whether the situation really calls for something that large.

Why B is the best answer

Focus areas describe where your attention is, not stages that lock behind you. A changed delivery date is a reason to plan again for the work it touches, to assess the change and to carry on with what is not affected.

Why the others fall short

  • ALogging the change and carrying on leaves the schedule and the budget wrong. The plan has to change too.
  • CStopping everything is an overreaction. Only the work touched by the change needs to be re-planned.
  • DOne late delivery is not a reason to close a project. Closing means the work is accepted and finished.

Where this question lives on the map

This question is about the whole map, not one process.

The same idea in a small business

A customer moves a delivery date and you re-plan that job, not the whole business.

Practice cardConcept

Which of these is a domain rather than a focus area?

How sure are you?

Read it like a test-taker

The phrase that decides the question is a domain rather than a focus area. Study habit: sort the options into two lists, "when" and "what". Only one option belongs in the other list.

Why C is the best answer

Domains say what the work is about, and PMI's own page names the seven as governance, scope, schedule, finance, stakeholders, resources and risk. Executing, closing and planning are focus areas: they say where you are in the work.

Why the others fall short

  • AExecuting is a focus area. It says that the work is being done.
  • BClosing is a focus area. It says that the work is being finished.
  • DPlanning is a focus area. It says that the team is working out how.

Where this question lives on the map

This question is about the whole map, not one process.

The same idea in a small business

"What topic is it?" is a domain question. "What stage are we in?" is a focus-area question.

Practice cardProcess 1.7 · Monitor and Control Project PerformanceScenario

Every week, three team members report progress on three different tasks and nobody compares it with the plan. Which process is missing, and in which focus area does it sit?

How sure are you?

Read it like a test-taker

The phrase that decides the question is nobody compares it with the plan. Study habit: look for the verb in the problem ("compares", "approves", "starts", "finishes") and match it to the focus area.

Why B is the best answer

Comparing what is happening with the plan, and deciding what to do about the gap, is what monitoring and controlling is for. The reports exist; the comparison is missing.

Why the others fall short

  • AThe work is being done and reported. Execution is not the gap.
  • CA schedule may exist. The problem is that nobody checks progress against it.
  • DThe project is not finished, so nothing is ready to close.

Where this question lives on the map

1.7 Monitor and Control Project Performance
Compare what is happening with the plan and decide what to do about the gap.

The same idea in a small business

In a five-person business, the missing piece is usually one page, once a week, that sets progress beside the plan.

Practice cardScenario

A project manager skips the risk and change processes entirely because "the project is small." What is the best assessment?

How sure are you?

Read it like a test-taker

The phrase that decides the question is skips the risk and change processes entirely. Study habit: "entirely" and "only" are often the words that mark an option as too extreme.

Why B is the best answer

PMI describes process guidance as non-prescriptive and speaks of tailoring for your context. Tailoring adjusts depth. Even a small project can meet a surprise or a change request, so a short, deliberate version of each process stays.

Why the others fall short

  • AA small project can still have a risk that matters and a customer who changes their mind. Skipping them silently is the gap.
  • CNothing requires all 40 in full. That would be the opposite mistake.
  • DTailoring is normally led by the project team with the sponsor's agreement, not reserved for the sponsor.

Where this question lives on the map

This question is about the whole map, not one process.

The same idea in a small business

Ten minutes on "what could go wrong" and a one-line rule for changes is a short version.

Practice cardProcess 1.3 · Plan Sourcing StrategyScenario

A team signs a cost-reimbursement contract for work whose requirements are still unknown, and it has no written sourcing approach. Which process was not done well?

How sure are you?

Read it like a test-taker

The phrase that decides the question is requirements are still unknown. Study habit: match the verb in the problem ("signs a contract", "chooses a supplier") to the process that owns it.

Why A is the best answer

Deciding what to build and what to buy, and how to choose and contract a supplier, is the job of the sourcing strategy. Choosing a contract type before the requirements are understood is the gap.

Why the others fall short

  • BClosing comes at the end of the work and is not the issue here.
  • CValidating scope is accepting finished deliverables. Nothing has been delivered yet.
  • DCommunications monitoring checks that messages land. The question is about the contract.

Where this question lives on the map

1.3 Plan Sourcing Strategy
Decide what you will build yourself and what you will buy, hire or rent, and how you will choose the supplier.

The same idea in a small business

Do not sign a contract that pays for hours when you cannot describe the work yet. Agree on a small first step.

Practice cardProcess 1.7 · Monitor and Control Project PerformanceScenario

A public launch is five weeks away. The performance tests were never run, and a go or no-go decision is due. What is the best action?

How sure are you?

Read it like a test-taker

The phrase that decides the question is performance tests were never run. Study habit: when a decision is described without evidence, the best answer usually creates the evidence first.

Why B is the best answer

A go or no-go decision is only as good as its evidence. Running the tests first lets the owner decide between launching, delaying or cutting scope on facts and not on hope.

Why the others fall short

  • ALaunching without verifying performance is the pattern that the GAO report describes in the Healthcare.gov case.
  • CCancelling is an overreaction to a problem that evidence can still address.
  • DRemoving the tests removes the evidence, not the risk.

Where this question lives on the map

1.7 Monitor and Control Project Performance
Compare what is happening with the plan and decide what to do about the gap.

The same idea in a small business

A shop that opens on a date without testing the payment system is betting its first day.

Practice cardProcess 1.1 · Initiate Project or PhaseScenario

A project starts with enthusiasm, but nobody can say who is accountable for it or what success looks like. Which process was done too thinly?

How sure are you?

Read it like a test-taker

The phrase that decides the question is nobody can say who is accountable. Study habit: ask where in the life of the work the problem sits. A missing owner is a beginning problem.

Why A is the best answer

Initiating is where someone decides the project should exist, says why and names who is in charge. Without an accountable owner and a definition of success, the project has not really been started.

Why the others fall short

  • BMonitoring risks needs a project that exists. The gap here is earlier.
  • CValidating scope is accepting finished deliverables, which comes much later.
  • DClosing is the end of the work, not the beginning.

Where this question lives on the map

1.1 Initiate Project or Phase
Decide that the project (or the next phase) should start, say why, and name who is in charge.

The same idea in a small business

Write the owner's name and one sentence of success at the top of a page before the first meeting.

Practice cardProcess 1.2 · Integrate and Align Project PlansScenario

The schedule assumes ten people. The budget, written by a different person, pays for six. What is the best action?

How sure are you?

Read it like a test-taker

The phrase that decides the question is written by a different person. Study habit: when a question describes two documents that disagree, the answer usually brings them together.

Why B is the best answer

Integrating and aligning the plans means reading them side by side, finding contradictions and resolving them into one plan. A schedule and a budget that disagree about the people are a classic contradiction.

Why the others fall short

  • ATwo plans that disagree are not two options. They are a gap that has to be closed.
  • CQuietly changing quality is a hidden change that creates a different problem later.
  • DWaiting for the problem to appear in a report turns a planning gap into a cost.

Where this question lives on the map

1.2 Integrate and Align Project Plans
Pull the separate plans (scope, schedule, money, people, risk) into one plan that does not contradict itself.

The same idea in a small business

One page with the six lines (scope, schedule, money, people, risk, and the thing most likely to break) shows contradictions fast.

Practice cardProcess 1.3 · Plan Sourcing StrategyScenario

A team must decide whether to build a feature in-house or buy a product. The need is stable and a standard product exists. What is the best way to use the sourcing decision?

How sure are you?

Read it like a test-taker

The phrase that decides the question is build a feature in-house or buy a product. Study habit: options with "always" or "most expensive" are often too blunt.

Why B is the best answer

A sourcing strategy compares the options against the same criteria and writes down the choice. With a stable need and a standard product, buying may well win, but the point is that the comparison is made.

Why the others fall short

  • A"Always" ignores the situation. Building can be right, but not by default.
  • CPrice is not a proxy for fit or safety.
  • DPostponing the decision leaves the work without a supplier or a plan.

Where this question lives on the map

1.3 Plan Sourcing Strategy
Decide what you will build yourself and what you will buy, hire or rent, and how you will choose the supplier.

The same idea in a small business

Put build and buy side by side on one page, with cost, time, risk and fit, and keep the page.

Cards also live inside the chapters, right after the part they test. Ch 1 · Ch 2 · Ch 3 · Ch 4 · Ch 5