The short answer
What is tailoring in PMBOK 8?
Tailoring is choosing how deep to go on each process, not whether you think about scope, money, people and risk. You always do. You decide how much paper it takes, and you write down what you left out and why.
After this chapter you can
- Take the three measurements (size, risk, uncertainty) of a real project
- Build your own one-page list of processes in five minutes
- Write one honest line for each process you leave out
Warm-up: take a guess first30 seconds. Guessing before you read helps the answer stick, even when the guess is wrong.
You skip a process on a small project. When is that fine, and when is it a problem?
The answer. Skipping is fine when you decide to, for a reason. It becomes a problem when you skip it silently. Write one line: what you left out and why.
The suit that fits nobody
There is an old joke about off-the-rack suits: they are cut for an average man who does not exist. The same is true of a method written for every project in the world. The PMBOK Guide has to cover a bridge, a software release, a wedding and a merger, so it is written at a height from which all four look the same.
That is why the Eighth Edition leans so hard on the word tailoring. PMI's page for the Guide lists "tailor for your context" among the things you will learn: how to adapt practices, tools and techniques to your team, organization and environment. It also describes the reintroduced process guidance as "non-prescriptive." Put the two together and the message is plain. The Guide is the bolt of cloth. You are the one who has to measure the person and cut.
Most people hear "tailoring" and think "doing less." That is half the idea, and the safer half. The other half is "doing more where it matters." A good tailor takes in the waist and lets out the shoulders in the same fitting.
What tailoring is not
Before the method, let me clear away three misunderstandings that I see all the time.
Tailoring is not skipping. If you leave a process out, you have made a decision, and decisions need an owner and a reason. "We did not do risk planning" is a gap. "We did a ten-minute risk review instead of a risk workshop because the project is two weeks long and the biggest risk is a late delivery, which one person watches" is tailoring.
Tailoring is not a license for chaos. A project with no owner, no numbers, no weekly look and no way of handling change is not tailored, it is unattended. The foundations in this guide (the Project Focus four: owner, three numbers, rhythm, control) are the part of the suit that does not get cut away.
Tailoring is not a one-time event. Projects change size, risk and certainty while they run. A pilot that grows into a program needs a bigger suit. Re-measure at every major decision.
The three measurements
When I tailor, I take three measurements. You can do this in five minutes with a pen.
- Size. How many people, how much money, how many months? A five-person, two-week job and a fifty-person, two-year program are not the same animal.
- Risk. What happens if it goes wrong? A broken internal report is an irritation. A broken public launch is a headline.
- Uncertainty. How well do you know what you are building? If the requirements are clear and stable, you can plan in detail. If they are not, you plan in short cycles and learn as you go.
These three drive almost every tailoring decision. Large, risky or uncertain projects get more process in the places where those things bite. Small, safe, well-understood projects get a short version.
The one-page core
If I had to name the part that never gets cut, I would say this: ten processes, one page, any project. They are an initiating, an aligning, an executing, a checking, a changing and a closing on the Governance row, plus the one list of who matters, a written scope, a schedule and a budget.
In the map's numbering: 1.1 Initiate Project or Phase, 1.2 Integrate and Align Project Plans, 1.4 Manage Project Execution, 1.7 Monitor and Control Project Performance, 1.8 Assess and Implement Changes, 1.9 Close Project or Phase, 5.1 Identify Stakeholders, 2.3 Define Scope, 3.2 Develop Schedule and 4.3 Develop Budget. That list is my own selection, labelled as such. You can disagree with it, and I would love to hear which one you would swap.
The case: Healthcare.gov, read as a tailoring story
The case I use for this chapter is Healthcare.gov, the federal health insurance marketplace website that opened for enrollment on October 1, 2013. Everything below comes from the U.S. Government Accountability Office, report GAO-14-694, published July 30, 2014, which I read on 2026-11-21. I am telling you what the report says, in neutral terms, and I am not offering opinions about anyone's politics or competence.

What the GAO says happened. The report states that the Centers for Medicare and Medicaid Services (CMS) undertook the development of the marketplace "without effective planning or oversight practices," and that it launched without verifying performance requirements. It adds that task orders were issued when key requirements were unknown, that cost-reimbursement contracts were used, that no required acquisition strategy was developed and that quality assurance plans were not used to monitor performance.
The timeline and the numbers. Initial enrollment began on October 1, 2013. A readiness review had moved from March to September 2013, just weeks before launch. Obligations for the federally facilitated marketplace rose from $56 million to more than $209 million between September 2011 and February 2014, and for the data hub from $30 million to nearly $85 million.
What happened next. GAO made five recommendations. Its page lists all five as closed and implemented, and records that CMS agreed with four and partly agreed with one.
Reading the case on the map
I read this as a case about tailoring done too thin. In the language of the map, the report describes gaps in six places. These are my mapping, not GAO's.
- 1.3 Plan Sourcing Strategy. No required acquisition strategy was developed, and cost-reimbursement contracts were used when requirements were unknown. That is a sourcing choice made before the work was understood.
- 2.2 Elicit and Analyze Requirements. Task orders were issued when key requirements were unknown.
- 1.5 Manage Quality Assurance. Quality assurance plans were not used to monitor performance.
- 1.7 Monitor and Control Project Performance. The marketplace launched without verified performance requirements, and the readiness review moved to just weeks before launch.
- 4.4 Monitor and Control Finances. Obligations rose substantially over the period.
- 1.1 Initiate and 1.2 Integrate: the "without effective planning or oversight" statement points at the first and second processes, which are the ones that are supposed to put a clear owner and a joined-up plan in place.
The lesson is not "do all 40." The lesson is that this project's size, risk and uncertainty were all high, and the tailoring did not rise to meet them.

How to tailor in five minutes
Here is the method as a recipe. Pick a project, and take a pen.
- Measure. Write the three measurements: size, risk and uncertainty, each as low, medium or high.
- Start from the core. Write down the ten processes of the one-page core. Do each one in the smallest honest way.
- Add by measurement. High risk adds the risk processes and quality assurance. A bigger team adds engagement, communications and resource processes. High uncertainty adds requirements and scope control. Buying outside work adds sourcing.
- Write the omissions. List what you left out. One line each: "Left out 6.3 Acquire Resources because the team is already in place."
- Re-measure at every big decision. Tailoring is a living page.
The tool below does steps one to four for you.
What tailoring looks like in different settings
The same recipe produces very different pages, and that is the point.
A two-week internal project with a team of three: the one-page core and nothing else. The weekly look is a ten-minute chat. The "closing" is a note in the team channel.
A six-month customer project with twelve people: the core, plus risk, plus stakeholder engagement and communications, plus resource planning. The weekly look is a half-page report. Changes go through a written form.
A public launch with real money and real people: the whole map is on the table. A named owner, independent testing before a go decision and a sourcing strategy before a contract are not optional extras, because the cost of a mistake is public.
If you want to read more about how methods differ, project management methodologies compared and agile, waterfall or hybrid set out the options, and lean project management shows how to cut waste without cutting thinking.
Four tailoring mistakes I see most often
After enough projects, the mistakes start to repeat, and it helps to know their names. These come from my own experience, so I mark them as my reading.
- Tailoring by mood. The team skips a process because it is boring, not because it is unneeded. The test is the one-line reason. "It is boring" does not survive being written down.
- Tailoring once and forgetting. The plan was sized for a pilot, the pilot became a program and the plan stayed pilot-sized. Put a re-measure on the calendar at every major decision.
- Copying someone else's tailoring. A page that fit a ten-person software team will not fit a construction crew. Borrow the method, not the page.
- Tailoring the paperwork but not the thinking. Cutting a form is easy. The harder and more valuable question is whether anyone still asks what could go wrong, who decides changes and what the three numbers are.
If you remember only one rule, make it this one: tailor the paper, never the questions. The questions are the project. The paper is how you remember the answers.
A quick way to check yourself is to read your own page aloud to someone who was not in the room. If they can tell you, in their own words, who owns the project, what the three numbers are, when you look at them and who can say yes to a change, the page is the right size. If they cannot, it is either too thin to carry the project or too thick to be read, and both are tailoring failures.
Where this connects
Tailoring touches nearly every article on this site. The project management plan guide shows a one-page plan and the project charter guide its front door. The contract risks that cost projects article is the sourcing half of the Healthcare.gov lesson. The status report guide is the weekly look. For changes, see change orders in construction and how to stop scope creep. For the schedule and the risk, the schedule management guide and the risk register for a small business. And for closing, project closeout and lessons learned.
How it connects
Same problem, other angle: articles on this site
Processes on the map this chapter touches
Make it stick
A picture, a phrase and a flip card do more for memory than a second read. Spend two minutes here.
Memory hook
Measure the suit
S-R-U: Size, Risk, Uncertainty.
Try this. Picture a tailor with a tape measure around a snowman (size), sewing a fire extinguisher into the lining (risk) and choosing a fabric that changes color while he cuts (uncertainty).
Memory hook
Six verbs and four questions
The one-page core: Start, Align, Do, Watch, Change, Close, then Who, What, When, How much.
Try this. Ten processes on one page: six verbs along the top (1.1, 1.2, 1.4, 1.7, 1.8, 1.9) and four questions along the bottom (5.1 who, 2.3 what, 3.2 when, 4.3 how much).
Flip cards: say the answer out loud before you flip
Practice questions
Teach it back
Tailor your own project out loud: tell a friend the three measurements, the ten core processes and the two you chose to leave out.
Where you get stuck is the exact paragraph to read again. Come back in three days: the 5-minute review will have these questions ready.
What to do next
If you have ten minutes, run the tool above on a project you know and compare the result with what you actually do. If you have an hour, read chapter 5 on Governance, where the one-page core starts. If you have a project with a launch date and no evidence, the two-minute diagnostic will point at the engine to fix first.
Frequently asked questions
Do I have to use all 40 processes?
PMI describes the process guidance as non-prescriptive and lists tailoring for your context among the things the Guide teaches. In practice you decide how deep to go on each one, and you write down what you left out and why.
What is the difference between tailoring and cutting corners?
Tailoring is a deliberate, written decision matched to the project's size, risk and uncertainty. Cutting corners is leaving something out without deciding. The test is simple: can you say why, in one line?
What is the minimum I should always do?
In this guide I use a one-page core of ten processes: initiate, align the plans, run the work, check performance, handle changes, close, identify stakeholders, define scope, build the schedule and build the budget. It is my selection, not PMI's.
Does the Healthcare.gov case prove that more process would have worked?
No. The GAO report describes weak planning, oversight and verification, but one report cannot tell you what would have happened otherwise. I use it as a case about tailoring too little for a project of that size and risk.
Sources and what they support
- PMI: PMBOK Guide, Eighth Edition page Read 2026-11-22. tailoring listed among what the Guide teaches; process guidance presented in an evolved, non-prescriptive way.
- GAO: Healthcare.gov, ineffective planning and oversight practices (GAO-14-694) Read 2026-11-21. the findings on planning and oversight, contracts and acquisition strategy, quality assurance plans, the readiness review, the obligation figures and the five recommendations.
- Ricardo Vargas Read . his process flow helped me organize the information so it could be digested.