Chapter 5 of 19 · 12 min read

Governance I: start, align the plans, decide what to buy

What does governance mean in a small project?

A cork board with a single sheet of paper pinned at its center showing a simple hand-drawn star above three circles and a line, no readable words
A charter is one page: why, who, and three numbers.

The short answer

What does the first part of Governance cover?

Three processes. 1.1 starts the project and names its owner. 1.2 turns separate plans into one plan that agrees with itself. 1.3 decides what you build and what you buy. In a small business the charter fits on half a page.

After this chapter you can

  • Write a one-page charter with one owner, a reason and three numbers
  • Explain what "integrate and align" adds to a pile of separate plans
  • Use the I-15 case to explain one build-or-buy decision and its price
Warm-up: take a guess first30 seconds. Guessing before you read helps the answer stick, even when the guess is wrong.

A friend says, "We have a scope, a schedule and a budget, so the plan is done." What might still be missing?

Governance, in plain words

Governance sounds like a word for people in good suits sitting at the long end of a table. In this guide it means something simpler: who decides, and how do they decide?

Look at the first row of the map. Nine processes live there, and they stretch across every focus area, from initiating to closing. If the other six domains (scope, schedule, finance, stakeholders, resources and risk) are the departments, Governance is the front office that tells them what the project is and checks that they are all working on the same one.

I divide the nine into three groups, and each gets a chapter. This chapter is about the beginning: starting the project (1.1), aligning its plans (1.2) and deciding what to buy (1.3). The next chapter covers running the work (1.4 to 1.6). The one after covers checking, changing and closing (1.7 to 1.9).

11.1 InitiateDecide, say why, name the owner.
21.2 Integrate and alignOne plan that agrees with itself.
31.3 Plan sourcingBuild or buy, and how to choose.
The first three Governance processes, in the order you usually need them.

The plain-words lines for each process in this guide are my own, written for this book. Where I mark something "my reading," it is a teaching choice and not a quote from the Guide.

1.1 Initiate Project or Phase

In plain words: someone decides that this project, or this next phase, should start; says why; and names who is in charge.

That sentence has three parts, and each one is a place where projects go wrong.

Someone decides. A project that nobody has authorized is a hobby with a budget. In a company, the authorization might come from a sponsor or an executive. In a small business, it might be you, on a Tuesday, deciding that the shop needs a new point-of-sale system. Either way, the decision should be visible: written down, dated and known to the people who will do the work.

Says why. This is the value question from chapter 2. If you cannot say in one sentence who will be better off when the project finishes, you do not yet have a project, you have an itch.

Names who is in charge. One person. The word "team" does not count. A project with shared ownership has a talent for belonging to nobody on the days it matters most.

If you want the long version, the business case and charter article and the project charter guide walk through the ten parts of a full charter.

1.2 Integrate and Align Project Plans

In plain words: pull the separate plans into one plan that does not contradict itself.

Projects tend to produce plans the way offices produce coffee cups: one at a time, in different places, and with nobody noticing how many there are. The schedule is written by the person who knows the work. The budget is built by the person who knows the numbers. The risk list comes from the meeting where everyone is worried. Each document is reasonable. Together they can be impossible.

I have seen a schedule that assumed ten people on a project whose budget paid for six. Nobody lied. Two people wrote two honest documents and the contradiction sat in the folder for a month.

Integration is the process that catches this. It is the moment where someone reads all the plans side by side and asks the awkward questions: does the schedule match the people we can pay for? Does the risk response have a budget? Does the scope fit the dates?

I find a one-page view the most useful tool here, a single sheet with six lines: scope, schedule, money, people, risk, and the one thing most likely to break. The sheet is not a replacement for the detailed plans. It is the place where they have to agree.

On the map, you can see why this process is in the Governance row: the arrows from scope, schedule, finance, resources and risk all feed into it. That is my reading of how the processes connect, and the page says so.

For a longer treatment of the written plan, see the project management plan guide.

1.3 Plan Sourcing Strategy

In plain words: decide what you will build yourself and what you will buy, hire or rent, and how you will choose the supplier.

Sourcing is the decision that is easiest to skip and most expensive to get wrong. Every project meets it, even small ones. Do you build the website or hire an agency? Do you hire a full-time employee or a contractor? Do you buy the software off the shelf or have it made?

A sourcing strategy answers four questions.

  1. Build or buy? Compare cost, time, risk and fit, and write down the answer. Many teams skip the comparison because the answer feels obvious. It is obvious until the quotes arrive.
  2. How will we choose? Price alone? Price and quality? Track record? The rule should exist before the proposals arrive, not after.
  3. What kind of contract? A fixed price suits work you can describe. A pay-as-you-go arrangement suits work you cannot yet. Choosing the contract type before you understand the work is the most common mistake, and it is the one the Healthcare.gov case in the previous chapter describes.
  4. Who on our side owns each supplier? Every outside party needs one named person on your team who watches the deliverables, the dates and the invoices.
Two wooden chairs side by side in a bright workshop, one handmade with visible joinery and one assembled from factory-made parts, no people and no text
Build or buy: both can be right. The decision should be written down.

For the contract risks that travel with this process, read contract risks that cost projects.

The case: the I-15 reconstruction in Utah

The case for this chapter is a good news story about sourcing, and it happened in our own back yard. The I-15 Reconstruction project rebuilt the interstate through Salt Lake County ahead of the 2002 Winter Olympics. Everything below comes from the Federal Highway Administration (FHWA) project profile, which I read on 2026-11-21.

The numbers. Construction began in April 1997 and was completed in July 2001. The project covered 16.2 miles of mainline and more than 130 bridges. It cost $1.63 billion, of which $448 million was federal and $1.184 billion was state and local money.

The sourcing choice. It was the Utah Department of Transportation's first design-build procurement. The award was made on a best-value basis to Wasatch Constructors, and state law was changed to allow best-value awards. Incentives of up to $50 million were part of the arrangement. The maintenance term was cut to a maximum of 10 years, and a wrap-up insurance program saved about $30 million.

A highway interchange under construction at dawn with temporary lane markers and bridge decks, no vehicles, no people and no text
Illustration of a large road project, not a photograph of the I-15 site.

A note on dates. A second FHWA page says the Salt Lake segment was completed in May 2001, before the Games, and that Utah hired a public relations firm to manage the impacts. That page is about a different project and mentions this one in passing, so I treat the July 2001 date on the project profile as the main one and flag the difference as unresolved. Final cost also differs by page ($1.63 billion on the profile, $1.59 billion elsewhere).

I-15 Reconstruction, UtahFHWA project profile
ConstructionApril 1997 to July 2001
Size16.2 miles of mainline, more than 130 bridges
Cost$1.63 billion ($448 million federal; $1.184 billion state and local)
ProcurementUDOT's first design-build, a best-value award
IncentivesUp to $50 million
OtherMaintenance term of at most 10 years; wrap-up insurance saved about $30 million
Facts from the FHWA project profile, read 2026-11-21.

Reading the case on the map

My reading, labelled as mine.

  • 1.1 Initiate. The outside date was immovable: the 2002 Winter Olympics. A fixed date is a gift to a project owner, because it ends arguments about priorities.
  • 1.3 Plan Sourcing Strategy. A design-build contract puts design and construction under one party, which shortens the path from idea to concrete. Best-value award means price was not the only criterion. Incentives paid for speed. This is a sourcing strategy that matched the problem: a fixed date and a very large job.
  • 1.2 Integrate. Wrap-up insurance and the maintenance term are the kind of items that appear when someone reads the whole plan, not just the construction schedule.
  • Stakeholders. A communication effort aimed at drivers is described on the second page I read, though I could not confirm the details.

I do not know from the pages I read how the project was monitored week to week, so I will not describe it.

Why "or Phase" is in the name

Look again at the name of 1.1: Initiate Project or Phase. Those two little words matter more than they look. Large projects are not decided once. They are decided again at every phase: after the design is approved, before the building starts, before the launch. Each of those is a small initiating moment, and each deserves its own half page.

I find this the most underused idea in the whole Governance row. A phase gate is a chance to ask the three charter questions again, with new information: is this still worth doing, is the owner still the right owner, and are the three numbers still the three numbers? Most projects that go wrong did not go wrong at the start. They went wrong at a phase boundary where nobody asked.

For a small business, a "phase" can be as simple as "we finished the planning week, and on Monday we start doing." Say it out loud, write the date and confirm the owner. It takes three minutes and it has saved me from more than one quietly expanding project.

The same idea applies to sourcing. A sourcing decision made in week one deserves a second look when the requirements change. A supplier chosen for a stable job may not fit a job whose scope has grown. Revisit 1.3 when 1.8 (changes) says the work is no longer the work you bought.

A last practical note on 1.2. The integrated plan is not finished once. It is a living page that is updated whenever a change is approved, which is exactly how process 1.8 feeds back into it on the map. If your plan is older than the last change request, it is no longer the plan. It is a souvenir.

Try it: your one-page charter

The tool below asks six short questions and writes a half-page charter you can copy into an email. It runs in your browser and saves nothing outside it.

Loading the tool…

Where this connects

Governance is the thread through most of this site. The kickoff meeting agenda is the first meeting after initiating. The RACI chart guide puts names on duties. The stakeholder map builds the "who matters" list. For plans on one page, the project management plan guide, and for the first weeks after the signature, the handoff from signed yes to kickoff. The change orders in construction article connects to contracts, and construction management versus project management clarifies who does what on a job site. For schedule, see the schedule management guide.

How it connects

Chapter 5Governance I

Leads to

6. Governance II: run the work, build quality in, keep what you learnNext: run the work, build quality in and keep what you learn (1.4 to 1.6).Coming soon7. Governance III: control, change and closeThen: control the work, decide on changes and close (1.7 to 1.9).Coming soon

Processes on the map this chapter touches

1.1 Initiate Project or PhaseDecide that the project (or the next phase) should start, say why, and name who is in charge.1.2 Integrate and Align Project PlansPull the separate plans (scope, schedule, money, people, risk) into one plan that does not contradict itself.1.3 Plan Sourcing StrategyDecide what you will build yourself and what you will buy, hire or rent, and how you will choose the supplier.1.4 Manage Project ExecutionDo the work in the plan and keep the project moving: tasks, people and the changes that were approved.Coming soon2.3 Define ScopeWrite down what is in and what is out, in words everyone reads the same way.Coming soon3.2 Develop SchedulePut the work in order, estimate how long each piece takes and produce dates the team can commit to.Coming soon4.3 Develop BudgetAdd the estimates up, add a reserve and fix the approved budget you will measure against.Coming soon

Make it stick

A picture, a phrase and a flip card do more for memory than a second read. Spend two minutes here.

Memory hook

One Who, One Why, Three Numbers

Name the owner, say why, give three numbers: the date, the money and what done looks like.

Try this. Picture a single person (the Who) holding one big question mark (the Why) beside three numbered stones (date, money, done) stacked on a table.

Memory hook

Start, Join, Buy

1.1 Start it. 1.2 Join the plans. 1.3 Buy or build.

Try this. Say it like a drumbeat: Start it, Join it, Buy it. Three beats, three processes.

Flip cards: say the answer out loud before you flip

Swipe, or use the arrows

Practice questions

Swipe, or use the arrows

Practice cardProcess 1.1 · Initiate Project or PhaseScenario

A project starts with enthusiasm, but nobody can say who is accountable for it or what success looks like. Which process was done too thinly?

How sure are you?

Read it like a test-taker

The phrase that decides the question is nobody can say who is accountable. Study habit: ask where in the life of the work the problem sits. A missing owner is a beginning problem.

Why A is the best answer

Initiating is where someone decides the project should exist, says why and names who is in charge. Without an accountable owner and a definition of success, the project has not really been started.

Why the others fall short

  • BMonitoring risks needs a project that exists. The gap here is earlier.
  • CValidating scope is accepting finished deliverables, which comes much later.
  • DClosing is the end of the work, not the beginning.

Where this question lives on the map

1.1 Initiate Project or Phase
Decide that the project (or the next phase) should start, say why, and name who is in charge.

The same idea in a small business

Write the owner's name and one sentence of success at the top of a page before the first meeting.

Practice cardProcess 1.2 · Integrate and Align Project PlansScenario

The schedule assumes ten people. The budget, written by a different person, pays for six. What is the best action?

How sure are you?

Read it like a test-taker

The phrase that decides the question is written by a different person. Study habit: when a question describes two documents that disagree, the answer usually brings them together.

Why B is the best answer

Integrating and aligning the plans means reading them side by side, finding contradictions and resolving them into one plan. A schedule and a budget that disagree about the people are a classic contradiction.

Why the others fall short

  • ATwo plans that disagree are not two options. They are a gap that has to be closed.
  • CQuietly changing quality is a hidden change that creates a different problem later.
  • DWaiting for the problem to appear in a report turns a planning gap into a cost.

Where this question lives on the map

1.2 Integrate and Align Project Plans
Pull the separate plans (scope, schedule, money, people, risk) into one plan that does not contradict itself.

The same idea in a small business

One page with the six lines (scope, schedule, money, people, risk, and the thing most likely to break) shows contradictions fast.

Practice cardProcess 1.3 · Plan Sourcing StrategyScenario

A team must decide whether to build a feature in-house or buy a product. The need is stable and a standard product exists. What is the best way to use the sourcing decision?

How sure are you?

Read it like a test-taker

The phrase that decides the question is build a feature in-house or buy a product. Study habit: options with "always" or "most expensive" are often too blunt.

Why B is the best answer

A sourcing strategy compares the options against the same criteria and writes down the choice. With a stable need and a standard product, buying may well win, but the point is that the comparison is made.

Why the others fall short

  • A"Always" ignores the situation. Building can be right, but not by default.
  • CPrice is not a proxy for fit or safety.
  • DPostponing the decision leaves the work without a supplier or a plan.

Where this question lives on the map

1.3 Plan Sourcing Strategy
Decide what you will build yourself and what you will buy, hire or rent, and how you will choose the supplier.

The same idea in a small business

Put build and buy side by side on one page, with cost, time, risk and fit, and keep the page.

Teach it back

Read your one-page charter aloud to a friend. Wherever they ask "why?", that line is not finished yet.

Where you get stuck is the exact paragraph to read again. Come back in three days: the 5-minute review will have these questions ready.

What to do next

If you have ten minutes, use the charter tool above on a project you are thinking about. If you have an hour, read the next chapter (coming soon) on running the work, quality and knowledge. If you are choosing a supplier right now, the two-minute diagnostic tells you which engine of your business to look at first.

Frequently asked questions

What does governance mean in a small project?

It means who decides and how. In a five-person job it is one named owner, one page that says why the project exists, and one rule for how changes are approved.

Is a project charter the same as a project plan?

No. The charter says why the project exists, who is in charge and what success looks like. The plan says how it will be done. The charter comes first and is much shorter.

How do I decide between design-build and traditional contracting?

Compare them on the same criteria: how well the work is defined, how fixed the date is, who carries which risk and how much control you need. The I-15 case used a design-build, best-value procurement for a fixed date and a very large job. That does not mean it fits every project.

Was the I-15 project "on time"?

FHWA's profile gives construction from April 1997 to July 2001, and a second FHWA page mentions May 2001 for the Salt Lake segment. I could not reconcile the two, so I report both and do not claim a verdict.

Sources and what they support